Thurston County and Campus Projects Monthly Update
Updated: 04/15/08
This information is provided by the Department of General Administration's Engineering and Architecture Services. The report covers capital planning and construction for the state Capitol Campus and satellite areas. Please direct questions or comments to Carolyn Ingraham at (360) 902-7269.
This report details active and upcoming construction projects.
Projects Under Construction
![]() |
DOT Building Escalator Removal/Build New Center Core Stairway
Project Manager: Stacy Simpson, 902-0921
Start Date: September 2006
Anticipated Completion Date: April 2008
Project Purpose: Remove old energy-inefficient escalators and replace them with a central core stairway and two new elevators.
Project Activity: Elevators are completed and in use. The escalators have been removed and the steel stairway is installed and open for use. The remaining finish work continues.
General Administration Parking Garage
Contact: Darlena Heglund, 902-7321
Project Manager: Dave Scott, 902-0988
Start Date: May 2007
Anticipated Completion Date: July 2008
Project Purpose: Seal the driving surface of the upper (visitor) level of the parking garage and re-stripe parking stalls. Conduct structural analysis of concrete beams and make repairs. The concrete panels that form the driving surface of upper parking level are deteriorating due to water intrusion and use by oversized vehicles.
Project Activity: The asphalt driving surface of the top deck was patched and cracks filled in June 2007. SUVs, vans and pick-up trucks are no longer allowed to be parked on the upper level of the garage. Parking for these vehicles was moved to the west side of the GA Building. The panels will be repaired and the upper deck sealed and re-stripped.
Impacts: Move overweight/oversized (4,000-plus-pound) vehicles to other locations.
Highway License Building Fire and Domestic Water Separation
Project Manager: Stacy Simpson, 902-0921
Anticipated Start Date: October 2007
Anticipated Completion Date: April 2008
Project Purpose: Separate the building’s fire sprinkler water supply from the domestic water supply, to bring it up to current safety code.
Project Activity: The work is complete except for installation of the irrigation water meter by the city and landscape restoration.
232 Perry St NW Childcare Center
Project Manager: Vikki Poitra, 902-0977
Anticipated Start Date: January 2008
Anticipated Completion Date: June 2008
Project Purpose: Campus Childcare Center will relocate to this property in June 2008. The project is improving this existing building to meet program and licensing needs.
Project Activity: The building interior and envelope is being upgraded by replacing the roof, siding, doors and windows. Currently, the contractor is saw-cutting the concrete slab to accept new plumbing lines and building new interior walls.
Upcoming Construction Projects
Natural Resources Building (NRB) Leak Repairs
Project Manager: Stacy Simpson, 902-0921
Anticipated Start Date: September 2007
Anticipated Completion Date: April 2008
Project Purpose: Fix leaks that are causing structural and property damage in the old fitness room at the eastern end of the building. The project is nearly complete and the contractor is waiting for dry weather to seal the concrete.
Highways – Licenses Building PA system
Project Manager: Stacy Simpson, 902-0921
Anticipated Start Date: October 2007
Anticipated Completion Date: April 2008
Project Purpose: Install a public-address system on all seven floors for emergency announcements. Other devices will be added. The initial installation is complete.
Highways – Licenses Building Security Upgrades
Project Manager: Stacy Simpson, 902-0921
Anticipated Start Date: June 2008
Anticipated Completion Date: March 2009
Project Purpose: Make the building more secure.
Legislative Building – Modernization of Elevators 4 & 7
Project Manager: Dwayne Harkness, 902-0942
Anticipate Start Date: May 2008
Anticipated Completion Date: December 2008
Project Purpose: Modernize House of Representatives Elevator #4 and historic Dome Service Elevator #7. Legislative Building elevators 1, 2, 3, 5 and 6 were modernized during the 2005-’07 biennium. This project will complete the modernization of all of the building’s elevators, including new hoistway equipment, machine and other upgrades to elevator #4, and controls, safety and restorative improvements to elevator #7.
Project Activity: Finalization of construction documents and preparation for bidding.
Pritchard Building – Reroofing, Potential Exterior Repairs and Modernization of Elevator
Project Manager: Marziah Kiehn, 902-7244
Anticipate Start Date: June 2008
Anticipated Completion Date: September 2008
Project Purpose: This project completes some of the most emergent repair needs for the Pritchard Building. The roof is past its useful life; the elevator does not fully meet current codes; and there are areas of spalling (erosion, cracking and flaking of the masonry and concrete) and cracking of the building exterior, including the portico roof. Recent investigation has shown some unanticipated spalling inside the building.
Project Activity: Agreements have been signed with three separate firms for survey of the exterior, preparation of construction documents and preparation for bidding in May.





