|
Priority #
|
Issue Title
|
Summary of Issue
|
|
Dan Absher – General
Contractor
“…contractors
have a lot of concerns. I have broken
the contractor issues into two categories: Alternative Procurement Issues and
General Public Contracting Issues. I believe the legislature intended our
Board to focus on Alternative Procurement. As we look at the number of
general issues, it should be clear that we cannot possibly engage in
meaningful discussions about all those topics within any reasonable
timeframe. “
|
|
LIST “A” - ALTERNATIVE PROCUREMENT ISSUES
|
|
1
|
MACC timing on GC/CM Projects
|
The timing of the setting of the
MACC is not consistent among owners and projects. Contractors believe the
proper time to set the MACC is when Construction Drawings are complete enough
to get firm subcontractor bids (90-100%) complete.
|
|
2
|
Proper Allocation of Risk
|
Some owners are using GC/CM to
improperly shift the risk of escalation, inflation and other market factors
to contractors. This is resulting in attempts by public owners to have GC/CM
contractors pay for significant portions of public buildings.
|
|
3
|
Opening the Market to Smaller Local Contractors
|
|
|
4
|
Eligibility Issues
|
It is important that only owners
who are capable of properly managing alternative procurement projects be
given the authority to do so. It is also important that the proper projects
are selected for alternative procurement for the right reasons.
|
|
5
|
Bonding and Prequalification of
Subcontractors
|
We need to protect the statutory
right of the GC/CM to prequalify and bond subcontractors.
|
|
6
|
Study Alternative Procurement
methods of the Federal Government and other States
|
We may learn better ways to
procure construction projects by looking at how others do it.
|
|
7
|
Standardizing Specified General
Conditions and Reimbursables in GC/CM contracts.
|
We need to develop a standard best
practice for treatment of these overhead items.
|
|
8
|
Early Selection of Mechanical and
Electrical Subcontractors on GC/CM Projects
|
Projects would benefit greatly if
the GC/CM were allowed to bring the Mechanical and Electrical contractor on
board early to assist during the design phase, as is done in nearly all
private projects.
|
|
9
|
Consistency in Selection Processes
of Alternative Procurement Projects.
|
There are a wide range of
selection methods employed by owners.
|
|
10
|
Expense and Honorariums on
Design/Build Projects
|
The selection process is too
expensive for design-build. Honorariums do not reimburse contractors for
actual expenses.
|
|
11
|
Contractor Incentives
|
Properly applied incentives are a
good and valuable tool.
|
|
LIST “B” – GENERAL PUBLIC CONTRACTING ISSUES
|
|
1
|
Notice Provisions in Contracts
(Mike M. Johnson Case)
|
The Mike M. Johnson case
inappropriately allows owners to authorize additional work and not pay for it
if the contractor slips up on a technical procedural requirement.
|
|
2
|
Liability for Injuries to Employees
on Construction Sites
|
Stute and other Supreme Court
decisions have provided a method for injured employees to circumvent the
immunity granted employers under the Workers’ Compensation Act.
|
|
3
|
Proper Allocation of Risk for
Escalation and Inflation
|
|
|
4
|
Protecting and Strengthening the
Statute of Repose
|
The Statute of Repose protects
builders, developers, architects and engineers involved in a project’s
construction against claims that do not occur within six years after a
project’s completion. This statute has led to stability in pricing and
availability of liability insurance.
|
|
5
|
General Contractor Liability for
Safety Violations of Subcontractors
|
We need to protect the statutory
right of the GC/CM to prequalify and bond subcontractors.
|
|
6
|
General Contractor Liability for
Prevailing Wage Deficiencies of Subcontractors
|
Despite due diligence, General
Contractors are held liable for Prevailing Wage deficiencies of its
subcontractors even if the subcontractor and its employee conspired to
fraudulently avoid paying prevailing wages.
|
|
7
|
General Contractor Liability for
labor and materials of Defaulting Subcontractors
|
Suppliers and workers have
statutory payment protection at the expense of the General Contractor. Should
owners bear that risk?
|
|
8
|
Address the Expansion of Workers’
Compensation Benefit
|
The Avundes and Cockle cases have expanded
Workers’ Compensation benefits. At the same time employer immunity is
becoming obsolete on construction sites.
|
|
9
|
Develop a Model Procurement Code
for the State
|
Big task, but this would
streamline the construction process throughout the state, reducing lawsuits
and saving money. The Federal Government has done it, so should Washington state.
|
|
10
|
Mandatory Apprenticeship Quotas
|
Apprenticeship is the foundation
of the construction industry. Quotas and penalties do not create more
apprentices. We are on the tip of a workforce shortage, which will result in
contractors being improperly penalized for failure to meet apprenticeship
quotas.
|
|
11
|
Require Contracting Out for
Construction Work
|
|
|
12
|
Project Labor Agreements
|
Leave labor agreements to Contractors
and Unions. Do not mandate them.
|
|
13
|
Appropriate Fees for Architects
and Engineers
|
|
|
14
|
Repeal the Subcontractor Bid
Listing Statute
|
The computer age has changed the
way subcontractor quotes are taken on bid day. Subcontractors can control the
timing of and information they include in their bids. It is often not
possible to determine which subcontractor is low at bid time because of the
amount of exclusions and qualifications in bids.
|
|
15
|
Streamlining and Standardizing the
Environmental Permitting Process
|
|
|
16
|
Prohibit Public Owners from
Contracting with other Public Owners for Construction Work
|
|
|
17
|
Improving the Small Works Roster
Process
|
|
|
18
|
Developing Proper Standards for
Day Labor Limits
|
|
|
19
|
Owner Abuse of Statutory Retention
on Public Contracts
|
Statutory retention is for the
protection of the labor and material suppliers on the project. Owners
improperly use it as a tool to secure performance and negotiate final change
orders.
|
|
Gerald "Butch" Reifert – Design Industry
|
|
1
|
Low Bid Contractor Selection
|
The state currently uses low-bid
for most projects. This often results
in inexperienced contractors and is often not in the best interest of the
Project. A best value selection process may be better used. With the new high performance public buildings
law (green buildings), having quality contractors is becoming even more
important to project success, therefore the low-bid model should not be
mandatory. There is interest in looking at a best value model for contractor
selection, similar to that used by the federal government. This would allow
for past performance, qualifications to perform the work, and other critical
factors to be considered along with price. Alternatively, consider other
selection options, such as selecting the second lowest bid or true
prequalification for contractors
|
|
2
|
Compliance with Qualification
Based Selection (QBS) Laws
|
Some local governments are working
on the edge of compliance with state QBS laws for selecting A/E firms.
Examples include requesting fees in a “separate envelope” to be opened after
the interviews; requesting a “level of effort” in which respondents have to
estimate the number of worker hours that would be required to complete the
proposed contract. These practices should be investigated and prohibited.
|
|
3
|
Legislative expansion of
alternative public works contracting methods
|
Every year there are many bills
introduced in the legislature to expand the alternative public works
contracting laws. It would be beneficial if these proposals were referred to
CPARB prior to legislative action for an objective review of the issues and
merits of the reasons for expansion.
|
|
4
|
Design-Build-Leaseback Procurement
|
Some local governments are
expanding the use of alternative delivery to include methods that do not
appear to be authorized. One example is the design-build development of a
building that is leased back to the public owner. This is treated as a real
estate transaction that skirts the design/construction procurement laws. The
CPARB should investigate examples of this practice to determine if it is in
compliance with state law.
|
|
5
|
Reauthorization of the Alternative
Public Works Procurement Law
|
Support continuing the alternative
public works procurement law so that current projects can be completed and
currently authorized agencies can utilize the law. However, it is important
to keep its use restricted to larger projects performed by more sophisticated
projects and to not expand it to restrict expansion from smaller owners and
more simple projects. Any reauthorization should continue tracking data on
the projects for future evaluations.
|
|
6
|
Comparable Study of Design-Build
|
A study of the use of design-build
that is comparable to just completed JLARC study of GC/CM.
|
|
Rocky Sharp – Specialty
Contractor
|
|
1
|
Standardize Subcontracts
|
Sub contracts change from job to
job, if there was a standard sub contract that was part of the bid documents
the contractor would know up front his risk.
|
|
2
|
Change Orders
|
Improve the markup allowed to
enable subcontractor to recover cost plus profit. Overhead can be 20% for
smaller subcontractors.
|
|
3
|
Contractor Eligibility
|
Develop a new eligibility form
that would not allow CM to insert qualifications that allows them to
basically choose who they want.
|
|
4
|
General Conditions
|
CM to be responsible for general
conditions no different than if they were on a DBB project.
|
|
5
|
Project Delay
|
Allow sub to be compensated for
delays that the sub did not cause. Decide on a standard formula for
calculating delay costs.
|
|
6
|
Retention
|
Allow for retention to be released
timely. If sub has no issues on project their retention should be released to
them.
|
|
7
|
Change Approval
|
Subs may be directed to work on
change order but may not be able to bill for this change for months after
they have incurred costs. The sub ends up financing this work.
|
|
8
|
Substantially Complete
|
This should be after receiving
punch list.
|
|
Ed Kommers– Specialty
Contractor
|
|
1
|
Develop Standard subcontract terms
and conditions for contracts between GC/CM’s and subcontractors.
|
Many GC/CM agreements shift unfair
risk to subcontractors through a non negotiable bid requirement. Unlike
D-B-B, subs have no opportunity to negotiate terms.
|
|
|
1a. Obligate the GC/CM to
coordinate work between subcontractors and resolve disputes
|
Some GC/CM’s require coordination,
disputes, scope and scheduling issues to be worked out between subs prior to
input from the GC/CM.
|
|
|
1b.Allow subcontractors to recover
costs from GC/CM due to delay not caused by subcontractor
|
Many GC/CM’s only allow additional
time or compensation if owner pays. Some delays occur due to poor scheduling
by GC or other subs and are not due to Owner decisions.
|
|
|
1c. Allow realistic overhead and
profit on change orders
|
Change clauses often do not
recognize the actual costs of change orders, indirect costs or “overhead” of
a subcontractor.
|
|
|
1d. Allow realistic and practical
lien waivers
|
Some bond and retainage waivers
require sub to waive all additional compensation and claims through date of
progress instead of in the amount of the progress payment.
|
|
|
1e. Allow work scope customarily
accomplished by subcontractors
|
Design scope packages to Limit pre purchase of equipment
and the break up of mechanical packages. Exclude scope outside of the subs’
normal work and use allowances instead.
|
|
|
1f. Improve the DRB process to
allow representatives selected by the subcontractor and possibly prohibit
“informal DRB’s
|
Subs don’t get to pick DRB members
but may have to use the process. Informal DRB’s waste time and money and are
not binding and may not even be referred to in the dispute resolution
process.
|
|
2
|
Require owners and GC/CM’s
response to change order requests within a reasonable period of time.
|
Many contracts include cumbersome
and numerous procedural prerequisites requiring contractors and subs to finance
changes. Typically, owners do not have the same requirements to respond, even
until substantial completion.
|
|
3
|
Prohibit Incentive Provisions tied
to MACC contingency except for schedule milestones and buyout contingency.
|
GC/CMs may refuse to disburse
contingency for its intended uses and keep it to improve their fee.
|
|
4
|
Revise eligibility language and
establish scoring criteria or eliminate eligibility all together.
|
The eligibility language is goofy,
vague and encourages GC/CM’s to substitute new language. Scoring should be
clear.
|
|
5
|
General Public Works provisions
|
|
|
|
5a. Revise retainage
|
Allow retainage to be released or
bonded around by subs if wage and trust obligations are met. Prohibit
unreasonable use of “schedule of values” to increase retainage. Retainage statute needs major work.
|
|
|
5b. Provide relief from “Johnson”
|
Allow extra costs for legitimate
changes if Owner is not damaged by lack of notice.
|
|
|
5c. Uniform responsibility
criteria
|
Define specific language to
determine bidder responsibility, like DOT/GA
|
|
|
5d. Restrict “Reject all bids” for
good cause only
|
Hey, didn’t we spend all last
summer talking about this?
|
|
David D. Johnson –
Construction Trades Labor
|
|
1
|
Responsible Bidder definitions
under Design/Bid/Build
|
While definitions exist for small
works and procurement (43.19.1911) and Broader definitions for GC/CM, no definitive language exists for
Design/Bid/Build
|
|
2
|
Bid Shopping (Release of all
sub-tier awards)
|
Current statute only requires
announcement of HVAC, Plumbing, and Electrical subcontractors or if the
General Contractor will self perform within.
Requirements should be for all first-tier subcontractors to be
announced the day of bid opening.
|
|
3
|
Apprenticeship Utilization
|
Promote apprenticeship utilization
by higher education, hospitals, and other state construction projects. Particularly educational facilities to stay
in step with direction of Washington Learns ideology.
|
|
4
|
Turn-key Projects
|
Transparency in investment of
public resources, eliminate process that allows circumventing fair payment of
prevailing wages, apprenticeship utilization and tax revenue collection by
causing public building to be built, and leased or purchased thereafter,
without providing true opportunity for proper wages, conditions, apprentices
and lost taxable revenues.
|
|
5
|
Project Labor Agreements (PLAs)
|
PLAs are a viable tool for public
owners to predict the course of their project. Consider the viability of PLAs in GA
Construction Management.
|
|
6
|
Emphasis Local Markets
|
Discourage outsourcing of public
purchases and projects, encourage hiring in-state contractors, labor and
materials.
|
|
7
|
Owner/Operator Conditions
|
Require owner/operator contractors
and subcontractors to provide workers compensation insurance on self and all employees
|
|
Carolyn Crowson – OMWBE
|
|
1
|
Low Participation of minority
firms in public contracting
|
Lack of genuine outreach and
opportunity and inclusion of minority and women owned businesses in public
contracting continues to be a problem for ethnic communities and the Washington State economy.
|
|
2
|
Prime Contractor Planning and
Reporting
|
Without overall subcontractor
reporting on outreach strategies, goal setting and participation, it is
difficult to plan for and measure the usage of OMWBE certified firms.
|
|
3
|
Prompt Payment of vendors and
contractors
|
Need for a statute revision to
require prime contractors to pay subs and suppliers when their work is done,
not when the prime’s work is done or when the prime gets paid. Smaller
businesses depend on timely payments for cash flow.
|
|
4
|
Right size contracts and
subcontracts for small business
|
Size of contract/subcontracts
determines the ability of small business to bid and to be successful.
|
|
5
|
Waive or reduce performance bonds
and insurance requirements
|
For low risk, small subcontracts reduced
bonding and insurance makes smaller firms more competitive.
|
|
Olivia Yang – Higher Education
|
|
1
|
Retain
and Expand Authority for Alternative Contracting
|
Retain
authority for WSU and UW past sunset date.
Expand
authority to include regional four year universities
(WWU, EWU, CWU, TESC)
Include
consideration of the following to provided structure transition for new owners
a)
oversight mechanism
b)
contracting, coaching or mentoring by more "seasoned" owners
c)
standard specifications or spec templates
d) uniform pool of dispute
resolution resources
|
|
2
|
Issues
for Specific Alternative Contracting
a. specific
to GC/CM:
1)
Early selection of major subcontractors during design
2)
Bonding
b. specific to JOC:
1)
Increase number of contracts per owner, and raise
dollar limit per work order
|
2.a.1)
Early selection of major subcontractors during design:
As
owners, we believe it would be very helpful to have input of major
subcontractors (mech., elec. or others) during design phase, so that the
collaboration between designer, contractor and owner can happen before design
is developed and bid.
|
|
3
|
Outside
of Legislative Recommendation, and for
discussion
a.
Different ways of responding to Escalation and Market Conditions
b.
When to set the MACC
|
3.a. As owners, we would be interested in a best
practices discussion, from other owners, and from others, on how to best
respond to project impacts during periods of significant cost escalation, and
unstable market conditions. We think this discussion may be helpful in
informing any discussions directly related to the charge for this board, and
in any proposed changes in legislation.
|
|
John Lynch – General Administration
|
|
1
|
Remove the sunset
|
Make alternative public works a
permanent pert of state statute.
|
|
2
|
Add “Best Value” to APW
|
Best Value contractor selections
would allow the public owner to use qualifications, previous performance, and
other factors in addition to price to select construction contractors.
|
|
3
|
Better define APW users
|
Provide the Legislature a logical
and consistent rule for determining which public agencies are allowed to use
APW.
|
|
4
|
Allow major sub contractors to
participate in GC/CM pre-construction services
|
Improve mechanical and electrical
designs by better value engineering, constructability review, and drawing
coordination.
|
|
5
|
Simplify the APW processes
|
Consider removing public hearings,
dollar limits, and other restrictions.
|
|
6
|
Simplify the small works roster
and Limited Public Works rules
|
Using the Small Works Roster
should be easier and should save time compared to advertised bidding.
|
|
7
|
Allow alternatives to Payment and
Performance Bonds
|
Payment & performance bonds
are expensive and there may be alternatives that provide reasonable
protection.
|
|
8
|
Solve the “reject all bids” issue
|
Establish rules that will reduce
the ability for public agencies to reject all contractor bids without good
cause.
|
|
9
|
Remove subcontractor listing rules
|
Existing rules seem to do nothing
and can cause bid protests.
|
|
10
|
Remove Trench Excavation price
rule for bids
|
Existing rules seem to do nothing
and can cause bid protests.
|
|
Larry Byers – Insurance/Surety
Industry
|
|
1
|
GC/CM Shifting of Risk to
Subcontractors
|
Techniques for shifting greater
risk to Sub-contractors and/or not adequately compensating for such risk concern
sureties bonding those subcontractors.
These practices make it more difficult for a subcontractor to manage
its projects and may strain financial resources, thus increasing the
probability of a sub experiencing problems on a job and increasing the chance
of a bond claim/loss.
|
|
2
|
GC/CM Subcontractor Selection
Standards
|
Subjective prequalification
standards for subcontractors are given greater weight than the ability of the
subcontractor to provide a payment and performance bond. This can reduce competition among
subcontractors and eliminate qualified sub-contractors in favor of less
qualified contractors. Vague or
imprecise prequalification standards can give the appearance of favoritism or
unfair awarding of contracts.
|
|
3
|
Expanding GC/CM to Smaller Projects
and Inexperienced Owners.
|
There have been previous efforts
to allow GC/CM on projects below $10 million.
The JLARC study indicates that GC/CM is best suited for “larger
complex projects.”
|
|
4
|
Small Works Roster – Waiving Bonds
|
SB5249 proposed waiving bonding
requirements for contracts under $200,000.
We believe this type of legislation unnecessarily exposes taxpayers to
risk of loss from contractors that default on their projects through failure
to pay subcontractors and material suppliers and/or failure to build a
structure in accordance with the specifications of the contract. This would also eliminate a very objective
and tangible qualification for identifying responsible bidders. This would open the selection of a
contractor based on vague criteria that could be difficult for a bidding
contractor to meet.
|
|
5
|
Expanded Use of Job Order
Contracts
|
SBB 5250 proposed to expand the
use of job order contracts by the General Administration Department from 2 to
10. One concern we have in regard to job order contracts is that the
amalgamation of numerous small jobs into a single large Job Order Contract
may freeze smaller contractors out of the process who lack the capacity to
take on large multi-year Job Order Contract commitments.
|
|
Gary Ballew – Counties (of Cities/Counties/Ports)
|
|
1
|
Expansion of the usage of GC/CM
and design/build to all levels of government
|
RCW 39.10.051 (4) limits the use
of alternative procurement methods to Counties with populations greater than
450,000. This criterion prohibits the
use of these procurement tools in 36 of Washington’s 39 Counties. Allowing smaller public entities (with the
necessary capabilities to manage a GC/CM or design build projects) to utilize
this procurement tool will expand the available pool of experienced
contractors, and provide an enhanced competitive environment throughout the
State.
|
|
2
|
Reduction or elimination of
limitations based on dollar size
|
Projects that meet the criteria
for being good candidates for GC/CM and design build should be allowed to
utilize these construction methods, regardless of size.
|
|
3
|
Removal of the sunset clause for
RCW Chapter 39.10.
|
Design build and GC/CM represent
powerful tools for construction of public facilities. As performance of all levels of government
comes under closer scrutiny, the State should seek to expand, not restrict
the tools necessary to enhance performance.
|
|
Rodney Eng – Cities (of Cities/Counties/Ports)
|
|
1
|
Permanent removal of the sunset
clause for RCW Chapter 39.10.
|
Where GC/CM and design-build have
shown to be effective procurement methods for providing high quality products
with a high level of cost certainty on complex projects, shouldn’t these
procurement methods be made a permanent procurement option?
|
|
2
|
Public bodies authorized to use alternative
public works procurement methods.
|
1.
Design-build
and GC/CM are sophisticated procurement methods that need owners with a
certain level of skill, experience and understanding of the processes to
properly use them.
2.
Not
all public bodies should be allowed to use these alternative public works
methods, only those with the necessary skills, experience and understanding.
3.
The
current size and/or dollar limitations are, at best, only rough methods for
defining which owners have the necessary skills, experience and
understanding.
4.
Can
we develop a more efficient method that allows all public owners with the
necessary skills, experience and understanding to utilize alternative public
works methods while preventing unqualified public owners from using these processes?
|
|
3
|
Types of projects to use
alternative public works methods on.
|
1.
Not
all projects are appropriate for the use of alternative public works methods.
2.
There
may be several types of complex projects that are less than $10 million that
would benefit from being procured using an alternative public work method.
3.
Should
the $10 million threshold be lowered?
4.
Is
there a way of refining the definition of the type of “complex” projects that
would be appropriate to use alternative public works methods on?
5.
Are
design-build and GC/CM different enough that separate criteria should be
developed for determining what an “appropriate” project is? Specifically, if it is determined that
dollar thresholds should be retained, should there be different thresholds
for design-build and GC/CM?
|
|
Michael Mequet – Ports (of Cities/Counties/Ports)
|
|
GC/CM Issues:
|
|
1
|
MEP
|
Is there a way to bring the
electrical & mechanical subs on board for review of documents during the
design phase
|
|
2
|
Size of sub package
|
If a sub package is a high % of
the total cost can this package be negotiated rather than competitively bid
|
|
3
|
GC/risk transfer
|
Stop the prime from transferring
GC issues to the sub that the prime is being paid to perform and manage the
transfer of risk to subs
|
|
4
|
GC role
|
Better define GC role during
construction
|
|
OTHER:
|
|
5
|
Other states
|
What are other states doing in
alternative public works contracting
|
|
6
|
Pre-qualifying of primes and subs
|
The GC/CM rules allow some pre
qualifying of subs already, can this be extended to primes
|
|
Wendy Keller – Public Hospital Project Review Board
|
|
1
|
Legislative clarity - for using
GC/CM
|
More specific requirements for
& better definition of how public
entities should demonstrate public
benefit like a projects scheduling complexities, operational complexities and
a fiscal benefit of using GC/CM or other alternate contracting methods. (Not
using the process because the public entity wants to talk with their
contractor)
|
|
2
|
Consistent evaluation
Criteria ( of projects requesting use of alternate contracting methods )
|
Prepare some written minimum
expectations (for meeting all criteria) for using alternative project
delivery methods. Incorporate into legislation requiring a boards / bodies
who recommend or approve use of the alternative process to meet these minimum
criteria and provide documentation that criteria were met.
|
|
3
|
Minimum Participant Qualifications
for Public Entity use of alternative contracting methods.
|
Public entity should have well
developed contract Terms & Conditions which are based on contracts (used
by public entities) who completed a project using an alternate contracting
method. Even if project was not
successful – lessons learned can be valuable. Public entity should have staff
or contracted staff with experience in the process actively working on the
project. And, be able to demonstrate & certify their level of project
involvement & role prior to authorization to use an alternative process.
|
|
4
|
More Stringent Project
Effectiveness Evaluation Requirements
|
Develop specific criteria for the
evaluation of project using alternative contracting methods. Help solve the
public benefit question. Require public entities to pay for & complete
such evaluation using a qualified evaluator (someone not involved with the
project) as a condition of being authorization to use alternative contracting
methods.
|
|
5
|
Develop Project Management
Training & require participation
|
Require public entities to have
project managers, key staff & decision makers for the project attend at
least a basic course before managing a public construction contract (applies
especially to alternative contracting methods). Like how/when to set MACC,
establish profit levels, use of contingencies etc.
|
|
6
|
Provide Board or Public Authority
Training
|
In addition to creating more
specific requirements or criteria for use of alterative processes. Provide
training to ensure more consistency in authorizing use of any alternative
contracting methods.
|
|
7
|
Address Issues with Subcontracting
community
|
As contract terms, public entity
& contractor skills vary – so do how the subcontractors are selected and
compensated. There should be a study and some clearer guidelines developed to
ensuring fairness and competition which should then be conveyed to all public
entities to include within contract documents.
|
|
8
|
Addressing Risk in Contracts
for radical Market Conditions
|
Applies to all contracting
methods. Recommend developing some boilerplate to address more radical
changes in market conditions which will balance risk for both contracts and
the public entity.
|
|
Dan Vaught – School District Project Review Board
|
|
1
|
K-12 continue to use alternative
contracting options
|
The K-12 goal is to be able to
continue to use alternative contracting options for our capital improvements.
|
|
Representative Kathy
Haigh – House of Representatives (D)
|
|
1
|
Establish Data Collection System
that is consistent.
|
We need to be able to have
accountability of construction contracts to make good decisions as we
consider expansion of GC/CM
|
|
2
|
Develop specific recommendations to the legislature as we
move into session.
|
The controversy over the next
session will be intense since we have not developed data (sec #1) to
make this decision the preliminary recommendation will be important.
|
|
3
|
Develop a mission statement with
strong consensus by the committee.
|
A strong mission statement with
buy in from the members will give the strength and purpose this committee
will need through the next several years.
|
|
Appointment Pending –
House of Representatives (R)
|
|
|
|
|
|
Senator Phil Rockefeller
– Senate (D)
|
|
1
|
The choice of which method of
contracting to use is a key initial decision to be made.
|
The choice of which method of
contracting to use is a key initial decision to be made, assuming
that both methods have their place and legitimate role, and the present
state law contemplates that both are available. So what sorts of
buffers and safeguards are needed to assure that the non-traditional method
is not used when it ought not be used and how can we assure that when invoked
there is not only justification, but appropriate use by informed and
experienced and properly advised parties on both sides?
|
|
Senator Dave Schmidt –
Senate (R)
|